What Data Do You Need to Schedule Fleet Charging, and Where Do You Find It?
A smart charging schedule decides which vehicle charges when, at what power and in what order, making every vehicle leave on time with enough energy while the site stays within its grid limit.
Your fleet may already hold the data needed to make up the schedule. Where to find it? Look at the charging system, the route planning, the vehicles and the electricity meter. Bring those data sources together to create an optimised charge plan.
With which data do you build a charge schedule?
Four important questions/checks:
- When does each vehicle arrive?
- When does it leave again?
- How much energy does it need before then?
- How much power does the site have available in the hours in between?
With knowledge of arrival and departure times, we can define the charging window of each vehicle. The energy demand then defines how much each vehicle needs within that window, while the available power sets the cap for all vehicles combined. If one of these inputs is missing or wrong, the schedule will make assumptions, resulting in vehicles leaving half charged or creating new peaks.
When do vehicles arrive, and how long do they stay plugged in?
The most reliable answer can be found in the charging system, where every charging session is logged with a start time, an end time and the energy delivered. This shows when vehicles plug in and how long they stay connected. A not-so-accurate system is planned return times, because traffic, extra stops and late shifts all show up in the data, making it unreliable.
It’s also better to assess several weeks of sessions, including different weekdays. This will reveal the real pattern: which vehicles return early, always arrive late and how much time the fleet actually has to charge.
How does the charging system know when each vehicle leaves?
One thing a charging system cannot measure by itself is the departure time. There are three ways to determine it:
- A fixed default departure time per vehicle or per group.
- Let drivers set a departure time when they plug in.
- Import departure times from the route planning or shift rota, so the schedule follows the actual plan for the next day.
A fourth option will become more common in the coming years: the vehicle telling the charger itself. That’s where ISO 15118 comes in.
What is ISO 15118, and what changes on 1 January 2027?
ISO 15118 is an international standard that determines the communication between an EV and a charger through the charging cable (a shared language). Today, that conversation is still very limited: many AC chargers still mainly send a signal that tells the vehicle how much current it may draw, but the vehicle tells the charger very little in return.
But when both the vehicle and the charger support ISO 15118, they can exchange much richer information, such as sharing its battery level, how much energy it still needs and when the driver wants to leave. The charger can use that information to plan the charging session. This also allows the charger to recognise the vehicle automatically when it’s plugged in, without a card or app. This is called plug-and-charge.
ISO 15118-20
The most recent version of the standard is ISO 15118-20, which also covers bidirectional charging, where a vehicle can send energy back to the building or the grid (Vehicle-to-Grid).
ISO 15118-20 will be mandatory from 1 January 2027 through the Alternative Fuels Infrastructure Regulation (AFIR). This means that newly installed or renovated public charging points, as well as new or renovated private AC and DC charging points, must support this version from then on.
Starting from 2027, a depot with newly installed chargers will be able to finetune their charge schedule even more. However, the vehicle must support the standard too. A good schedule needs to handle both communicating and non-communicating vehicles.
More about ISO 15118-20 and what changes for charging sites from 2027
Sources: DEKRA, Applying for ISO 15118 certification?; EUR-Lex, Commission Delegated Regulation (EU) 2025/656 amending Regulation (EU) 2023/1804 (AFIR); ElaadNL, Technical requirements for purchasing and operating Smart and Bidirectional Charging, version 1.0
How much energy does each vehicle need if the charger cannot read the battery?
So, without ISO 15118 communication, the charger can only see how much energy flows during the session and when the vehicle stops drawing power because the battery is full.
Because of the unknown battery level, the schedule is unable to tell whether a van needs a short or a long charge. A nearly full van will then get the same priority as an almost empty one, or the power is spread when another vehicle needs it most for an early departure.
When the battery level is known, the schedule calculates exactly how much energy is still missing per vehicle, stops each session at the right moment and sends the remaining power to the vehicles that are still short.
As not every vehicle and charger in the fleet communicates via ISO 15118 yet, there are three ways to assess how much energy each vehicle needs:
- Route: the planned distance for the following day multiplied by the vehicle’s real consumption per kilometre, taken from its charging history or telematics.
- Previous session: yesterday’s session is a practical starting point to see how much it needed then for that route.
- Vehicle: many telematics platforms and manufacturer dashboards (such as our Smappee Dashboard) report the state of charge, which can be put into the schedule.
Seasons should also be considered
In ADAC’s long-term tests, electric cars used 25 to 31 percent more energy in winter, predominantly because the cabin and the battery need heating. Preheating while the vehicle is still plugged in draws that energy from the grid instead of the battery, so it’s worth planning it during the charging window.
Next to that, ADAC also noted that part of the energy drawn from the grid never reaches the battery. For example: at an 11 kW AC charger, they measured charging losses of 5.1 to 7.0 percent.
Sources: ADAC, E-Auto im Winter: Mehr Verbrauch, weniger Reichweite; ADAC, Ladeverluste beim Elektroauto: Wie hoch sind sie wirklich?
How does the schedule know which vehicle is plugged in?
It’s also important for the schedule to know which vehicle is connected to which charger but in practice that’s not always the case.
The three fixes:
- An RFID card per vehicle, where the card stays in the van: the moment someone plugs in and taps the card, the charger knows which vehicle is plugged in.
- Fixed charging bays: simple, but less flexible.
- Automatic vehicle identification: the car and charger have a two-way communication when plugged in. No need for a card or a fixed spot. This is the same technology as Plug & Charge at public stations. For this both the charger and car should be ISO 15118 compliant.
Sources: EUR-Lex, Commission Delegated Regulation (EU) 2025/656 amending Regulation (EU) 2023/1804 (AFIR)
How much power does the site have available, hour by hour?
The fourth source of data comes from your electricity meter. Commercial connections are usually measured per quarter of an hour, and those values show how much power the building consumes throughout the night. When you subtract that consumption from the connection limit, you’ll see how much capacity is left for charging in every quarter of an hour.
This data is typically available through the customer portal of the grid operator, the energy supplier or via the dashboard of your Energy Management System. It turns a fixed charging limit into a profile that follows the building: more room once lighting, heating and equipment switch off, and less when the first shift starts up.
Discover how charging and energy management work together at depot sites
In what order should vehicles charge?
When you’ve collected all this data, priority rules decide the order in which vehicles will charge. The most logical way to start the schedule is to charge the vehicle with the earliest departure first, followed by the vehicle with the largest energy gap. Just make sure to set a guaranteed minimum charge level for every vehicle, so that even a late arrival or an unexpected route leaves with enough energy.
It’s also worth to set-up a plan for what’s to happen when something goes differently. In practice, that comes down to a few typical cases:
- A vehicle returns later than planned: that means its charging window becomes shorter, so the schedule moves it up the priority list or gives it more power, while vehicles with a later departure charge more slowly for a while.
- A charger is out of service: the vehicle is moved to another charger, and the schedule redistributes the available power and charging time across the remaining chargers.
- A vehicle has to leave earlier: the new departure time is entered or imported, and the vehicle automatically gets priority over vehicles that leave later.
- Not all vehicles can be fully charged in time: every vehicle first receives its guaranteed minimum charge level, after which the remaining energy goes to the vehicles that leave first.
How do you know whether the schedule works?
The same session data that revealed the arrival pattern also shows whether the plan worked. The same checks as in the beginning matter:
- Did the vehicle receive the energy it needed?
- Is the vehicle ready before its departure time?
- Did the site stay under its power limit during the night?
Make sure to record interrupted and failed sessions too, as they are just as telling as completed ones. After the first few weeks, this also helps uncover which default needs adjusting.
Want to know why your charging session failed? Read our guide:
As fleets grow, charging shifts from a technical detail to a daily planning task. Much of the data that planning needs is already available in the charging system, the route planning and the meter. Bringing it together turns a fixed charging routine into a schedule that follows how the fleet operates, while keeping energy costs and grid capacity under control.